DUBUQUE, Iowa — November 27, 2026 — The City of Dubuque and the U.S. Army Corps of Engineers have proposed a $10.3 million plan, first reported by KCRG-TV9, to protect a sewer pipe along the Mississippi River that carries 65 percent of the city’s sewage, after erosion stripped away the riverbank that once shielded it.

The forced sewer main runs along the riverbank on the southern edge of Dubuque, south of the city’s floodwall. In places, the bank has eroded away entirely, leaving sections of the pipe exposed. The pipe itself is structurally sound, but without its bank protection it is vulnerable to damage from the river and from barges that park nearby and have occasionally run aground.

A break in the pipe would send about 4 million gallons of raw sewage a day into the Mississippi River, threatening downstream fish and water quality, and would shut down wastewater treatment for the city. The proposed fix would shore up the eroded bank with large rocks and gravel, known as riprap, and is expected to protect the pipe for another 40 years.

The Army Corps of Engineers has been working on the project for several years. A feasibility study was completed in March 2022, and design work has been underway since, but the effort has been delayed while the city and the Corps worked through concerns with two railroads whose land sits next to the pipe.

The pipe is a piece of critical infrastructure that most Dubuque residents never see. It carries the majority of the city’s wastewater to the Water and Resource Recovery Center. The Corps’ project area covers roughly 3,000 feet of shoreline along the river’s right descending bank, between river miles 577.7 and 578.4, ending just north of the parking lot at the end of Julien Dubuque Drive.

City officials have not said how the $10.3 million cost would be split between the city and the federal government, and that detail remains pending.